QUESTION 51

Which of the following activities are associated with a project kick-off meeting? (Select TWO).

 

A.     Obtaining a signature on the project charter.

B.     Communicating project goals and objectives.

C.     Communicating work package assignments.

D.     Creating a rough draft of the transition plan.

E.      Communicating stakeholder expectations.

 

Correct Answer: BE

 

 

QUESTION 52

When working to ensure the quality of project deliverables, which of the following steps must take place before variances can be identified? (Select TWO).

 

A.     Generate change requests.

B.     Perform impact analysis.

C.     Analyze performance information.

D.     Implement change requests.

E.      Monitor work performance.

 

Correct Answer: CE

 

 

QUESTION 53

Which of the following will reduce the impact of a project threat?

 

A.     Risk acceptance

B.     Risk enhancing

C.     Risk mitigation

D.     Risk monitoring

Correct Answer: C

 

 

QUESTION 54

The plan sponsor cancels a project prior to its completion. Which of the following should the project manager use to document the strengths and weaknesses of the project?

 

A.     Performance review

B.     Transition plan

C.     Summary of costs

D.     Lessons learned

 

Correct Answer: D

 

 

QUESTION 55

Which of the following is an indication of project closure?

 

A.     Removal of the key stakeholder

B.     Reduction of resources

C.     Project cancellation

D.     Project rescheduling

 

Correct Answer: C

 

 

QUESTION 56

Which of the following is the purpose of a post-project review?

 

A.     Analyzes project performance.

B.     Forms the control structure for the project.

C.     Manages stakeholder expectations.

D.     Identifies end products and intermediate deliverables.

 

Correct Answer: A

 

 

QUESTION 57

Which of the following estimating types requires the MOST effort when creating a work

breakdown structure (WBS)?

 

A.     Expert judgment

B.     Top-down

C.     Bottom-up

D.     Rough order of magnitude

 

Correct Answer: C

 

 

QUESTION 58

During which of the following phases should project requirements be determined?

 

A.     The initiating phase

B.     The execution phase

C.     The planning phase

D.     The monitoring phase

 

Correct Answer: A

 

 

QUESTION 59

A project has an earned value (EV) of $5,000 and $6,000 has been spent to date. Which of the following is the cost variance and status of the project?

 

A.     -$1,000 and under-budget

B.     $1,000 and under-budget

C.     -$1,000 and over-budget

D.     $1,000 and over-budget

 

Correct Answer: C

 

 

QUESTION 60

A project has an earned value (EV) of $5,000 and $6,000 has been spent to date. Which of the following is the cost performance index (CPI) and the project status?

 

A.     1.2 and over-budget

B.     0.83 and over-budget

C.     0.83 and under-budget

D.     1.2 and under-budget

 

Correct Answer: B

 