[Free] Download New Updated (December) CompTIA PK0-003 Exam Questions 271-280

Ensurepass

QUESTION 271

A conflict has developed among two project team members. The project manager reiterates the

areas of agreement and avoids the areas of disagreement. Which of the following BEST describes

this conflict resolution technique?

 

A.     Smoothing

B.     Compromising

C.     Avoiding

D.     Negotiating

 

Correct Answer: A

 

 

QUESTION 272

A stakeholder informed the project manager of an unauthorized modification to the project

deliverable. It appears that the modification will benefit the project and allow early completion.

Which of the following should the project manager do?

 

A.     The modification should be removed from the project until a change request is approved.

B.     The stakeholder should be required to review the remainder of the project to locate

additional improvements.

C.     Even though the modification might benefit the project, the stakeholder should be removed

from the remainder of the project and their manager should be notified.

D.     The modification should be noted in the change log and the project should be reviewed to

locate any negative impact.

 

Correct Answer: D

 

 

QUESTION 273

Which of the following is a common project selection method?

 

A.     Work Breakdown Structure (WBS)

B.     Benefit measurement

C.     User acceptance testing

D.     System design specification

 

Correct Answer: B

 

 

QUESTION 274

During which of the following phases is funding FIRST approved for the project?

 

A.     Planning

B.     Execution

C.     Monitoring

D.     Initiation

 

Correct Answer: D

 

 

QUESTION 275

Which of the following documents provides formal approval to start the project?

 

A.     Resource assignment matrix

B.     Project charter

C.     Work Breakdown Structure (WBS)

D.     Contract administration

 

Correct Answer: B

 

 

QUESTION 276

A project scope statement includes which of the following items? (Select THREE).

 

A.     Major deliverables

B.     Success criteria

C.     Constraints

D.     WBS

E.      Scope management plan

F.      Mandatory dependencies

 

Correct Answer: ABC

QUESTION 277

Which of the following directly utilize the WBS? (Select TWO).

 

A.     Communication plan

B.     Monte Carlo technique

C.     Activity estimation

D.     Variance analysis

E.      Resource assignment

 

Correct Answer: CE

 

 

QUESTION 278

Which of the following BEST identifies the correct number of layers in a WBS?

 

A.     WBS should decompose to a manageable level to use the activity.

B.     WBS decomposition depends on the complexity of the overall project.

C.     WBS should decompose until activities are broken into small, specific tasks.

D.     WBS decomposition has the same number of levels for all objectives.

 

Correct Answer: A

 

 

QUESTION 279

Click on the Exhibit button. Which of the following is the duration of the path: start-A-B-E-C-end?

 

clip_image002

 

A.     16

B.     17

C.     18

D.     19

 

Correct Answer: C

 

QUESTION 280

Click on the Exhibit button. Which of the following is the float of the path: start-A-D-end?

 

clip_image003

 

A.     Zero

B.     One

C.     Five

D.     Nineteen

 

Correct Answer: A

 