[Free] Download New Updated (December) CompTIA PK0-003 Exam Questions 181-190

Ensurepass

QUESTION 181

A WBS dictionary:

 

A.     is a granular hierarchical breakdown of the work to be undertaken by the project team, to

meet the objectives of the project

B.     provides a description of all of the components of a WBS, and a brief summary of its SOW,

scope and deliverables

C.     allocates the WBS components to appropriate teams or named individuals within teams

D.     describes how a project will be decomposed into smaller, manageable subprojects or work

packages

 

Correct Answer: B

 

 

QUESTION 182

Information gathering resources for an initial risk assessment for a project include. (Select THREE)

 

A.     precedence diagramming method

B.     SWOT analysis

C.     brainstorming

D.     crashing

E.      delphi technique

F.      critical chain method

 

Correct Answer: BCE

 

 

 

QUESTION 183

During the execution phase of a large scale project, a new stakeholder is identified that has vital information that could impact the completion of the project. Which of the following is the FIRST activity the project manager should undertake?

 

A.     Call a meeting of the key stakeholders to introduce the new stakeholder and discuss the new input/requirements.

B.     Halt the project immediately; accept any changes requested by the new stakeholder once all current stakeholders have been informed.

C.     Discuss the new stakeholder’s inputs/requirements with the project sponsor and take advice on the consequent actions.

D.     Request that the new stakeholder raise an urgent change request for authorization to change the scope of the project and submit it via the documented change request procedure.

 

Correct Answer: A

 

 

QUESTION 184

All of the following are found in the project scope document EXCEPT:

 

A.     scheduled milestones

B.     defined risks

C.     constraints

D.     WBS

 

Correct Answer: D

 

 

QUESTION 185

The value of the EV is $65,000, and the value of the AC is $40,000. Which of the following is the correct monetary value for the CV?

 

A.     $25,000

B.     $65,000

C.     -$65,000

D.     $105,000

 

Correct Answer: A

 

 

 

 

 

 

QUESTION 186

An ongoing project has a CV of $15,000 and an EV of $45,000. Which of the following represents the project’s AC?

 

A.     .33

B.     3

C.     $30,000

D.     $60,000

 

Correct Answer: C

 

 

QUESTION 187

Which of the following represents an ongoing project with a CPI equal to .9?

 

A.     AC is $90,000; EV is $100,000

B.     CV is $10,000; AC is $100,000

C.     CV is $10,000; EV is $100,000

D.     EV is $90,000; AC is $100,000

 

Correct Answer: D

 

 

QUESTION 188

Which of the following conclusions can be drawn when a project has a CPI of 1.2?

 

A.     The project is taking longer than the estimated schedule.

B.     The project is costing less than the estimated budget.

C.     The project is taking less time than the estimated schedule.

D.     The project is costing more than the estimated budget.

 

Correct Answer: B

 

 

QUESTION 189

Which of the following circumstances requires a project closure? (Select TWO).

 

A.     The project deliverables are not meeting quality standards.

B.     The project progresses beyond the scheduled end date.

C.     The project is over the allotted budget.

D.     The project activities and deliverables are completed.

E.      The project has been cancelled.

 

Correct Answer: DE

QUESTION 190

Which of the following project phases includes the transition plan?

 

A.     Executing

B.     Closing

C.     Planning

D.     Monitoring / Controlling

 

Correct Answer: B

 