QUESTION 71

Which of the following should be created in the project closing documentation? (Select Two).

 

A.

Closure report summarizing costs

B.

Responsibility assessment matrix

C.

Lessons learned

D.

Project timeline

E.

Statement of Work (SOW)

 

Correct Answer: AC

 

 

QUESTION 72

The project manager crashes a project that is behind schedule and under-budget. Which of the following will be the intended result?

 

A.

The project will be behind schedule and over-budget.

B.

The project will be on schedule but over-budget.

C.

The project will be on schedule and on-budget.

D.

The project will be behind schedule and on-budget.

 

Correct Answer: C

 

 

QUESTION 73

A project can be defined as which of the following?

 

A.

A high level cost estimate

B.

An ongoing work assignment

C.

A temporary endeavor with unlimited time or cost for completion

D.

A temporary endeavor limited by time or cost

 

Correct Answer: D

 

 

QUESTION 74

Several managers are sharing a project team member, which is impacting the progress of both projects. Which of the following BEST describes the situation?

 

A.

Varying work styles

B.

Schedule variance

C.

Scope creep

D.

Competing resource demands

 

Correct Answer: D

 

 

QUESTION 75

Refer to the attached Exhibit. Which of the following is the float of path Start-C-E-Finish in the network diagram?

 

clip_image002

 

A.

Zero

B.

One

C.

Three

D.

Five

 

Correct Answer: A

 

 

QUESTION 76

After final acceptance, which of the following would the project manager use to assess the strengths and weaknesses of the project?

 

A.

Post-project review

B.

Transition plan

C.

Project kick-off meeting

D.

Quality analysis

 

Correct Answer: A

 

 

QUESTION 77

The lessons-learned activity and formal acceptance documentation form part of which of the following process groups?

 

A.

Closing

B.

Planning

C.

Executing

D.

Monitoring/Controlling

 

Correct Answer: A

 

 

QUESTION 78

Which of the following occurs during a project kick-off meeting? (Select Two).

 

A.

Work performance information is established.

B.

Risk analysis is performed.

C.

Quality metrics are defined.

D.

Project goals are communicated.

E.

Roles and responsibilities of the project team are identified.

 

Correct Answer: DE

 

 

QUESTION 79

A project manager is conducting a root cause analysis with the project team. Which of the following tools should be utilized?

 

A.

Gantt chart

B.

Ishikawa diagram

C.

Network diagram

D.

Run chart

 

Correct Answer: B

 

 

QUESTION 80

Final project acceptance criteria are contained in which of the following?

 

A.

Transition plan

B.

Project scope document

C.

Project charter

D.

Quality plan

 

Correct Answer: B

 