QUESTION 231

Which of the following techniques could a project manager use to determine a project schedule based upon a variety of simulations?

 

A.

Schedule network analysis

B.

Critical chain method

C.

Critical path method

D.

Monte Carlo analysis

 

Correct Answer: D

 

 

QUESTION 232

A project manager needs to replace someone on the pr
oject team. Which of the following is the FIRST action they should take?

 

A.

Consult the project staffing plan.

B.

Notify the human resources department to open a job posting.

C.

Search for skilled subcontractors who could quickly fill the opening.

D.

Ask the project sponsor for another resource.

 

Correct Answer: A

 

 

QUESTION 233

Which of the following conclusions can be drawn when a project has a CPI of 1.2?

 

A.

The project is taking longer than the estimated schedule.

B.

The project is costing less than the estimated budget.

C.

The project is taking less time than the estimated schedule.

D.

The project is costing more than the estimated budget.

 

Correct Answer: B

 

QUESTION 234

Which of the following steps should a project manager take to ensure the quality of project deliverables for a customer? (Select Two).

 

A.

The project manager should consult the project sponsor and customer to review the current quality requirements.

B.

The project manager should request a peer review of the project to determine if it meets the customers quality standards.

C.

The project manager should change the scope of the project to meet the customers expectations of quality standards.

D.

The project manager should check the finished product to determine if it meets the customers quality standards.

E.

The project manager should outsource to obtain the best resources for the project.

 

Correct Answer: BD

 

 

QUESTION 235

In order to prepare a project charter, which of the following items are required for the pre- project setup?

 

A.

Assumptions, constraints, project deliverables, and all resources required for the project.

B.

Client name, client project manager, organization project manager, and a complete project budget.

C.

Direction from team members, development methodology, and staff requirements.

D.

Business need, assumptions, constraints, project deliverables, and staff requirements.

 

Correct Answer: D

 

 

QUESTION 236

A project team has increased from six to twelve resources. How many total communication paths exist after the addition of resources?

 

A.

24

B.

48

C.

66

D.

144

 

Correct Answer: C

 

 

QUESTION 237

In a highway project 5 miles (8 kilometers) out of the total 15 miles (24 kilometers) have been completed. The BAC is $900,000. Which of the following represents the EV of this project?

 

A.

$150,000

B.

$300,000

C.

$450,000

D.

$600,000

 

Correct Answer: B

 

QUESTION 238

All of the following are taken into account when determining the critical path EXCEPT:

 

A.

Late start and finish dates.

B.

Activity durations.

C.

Early start and finish dates.

D.

Resource limitations.

 

Correct Answer: D

 

 

QUESTION 239

Which of the following tools is the BEST to measure data organized in time sequence?

 

A.

Run chart

B.

Ishikawa diagram

C.

Pareto chart

D.

Histogram

 

Correct Answer: A

 

 

QUESTION 240

Which of the following is the MOST common relationship used, when constructing a project schedule network diagram?

 

A.

Start-to-Finish

B.

Finish-to-Start

C.

Start-to-Start

D.

Finish-to-Finish

 

Correct Answer: B

 