QUESTION 221

A project manager is completing a project schedule network diagram using dummy activities to show all logical relationships. Which of the following tools is the project manager using?

 

A.

ADM

B.

WBS

C.

AON

D.

PDM

 

Correct Answer: A

 

 

QUESTION 222

Which of the following would be the BEST tool to estimate activity time duration
s?

 

A.

Gantt chart

B.

CPM

C.

Estimating model

D.

PERT

 

Correct Answer: D

 

 

QUESTION 223

Which of the following is an input to a work breakdown structure (WBS)?

 

A.

Performance reports

B.

Stakeholder analysis

C.

Project scope statement

D.

Variance analysis

 

Correct Answer: C

 

 

QUESTION 224

The communication plan for a project is a subset of which of the following documents?

 

A.

Project charter

B.

Risk management plan

C.

Project schedule

D.

Project plan

 

Correct Answer: D

 

 

 

 

 

QUESTION 225

A new critical requirement has been identified after the project charter was approved. Which of the following is the NEXT step the project manager should take?

 

A.

Convene another meeting with the entire group reviewing the requirements one last time and incorporating the additional requirement.

B.

Determine the effort of the missing requirement and incorporate it into the work plan.

C.

Revise the approved requirements document and forward to the project team for review.

D.

Generate a change request and submit it to the change control board for review.

 

Correct Answer: D

 

 

QUESTION 226

A project has been cancelled during the execution phase. Which of the following steps should be taken?

 

A.

Continue to work the project.

B.

Finish the project charter and project plan.

C.

Complete lessons learned document.

D.

Develop the project transition plan.

 

Correct Answer: C

 

 

QUESTION 227

Which of the following documents should be used to present the length of identified tasks?

 

A.

CPM

B.

Key event/activity list

C.

PERT

D.

Gantt

 

Correct Answer: D

 

 

QUESTION 228

The method of cost-estimating whereby the costs of the individual work packages are aggregated to form the full cost-estimate is called:

 

A.

parametric estimating.

B.

bottom-up estimating.

C.

expert judgment.

D.

analogous estimating.

 

Correct Answer: B

 

 

QUESTION 229

The project scope document should outline which of the following project items? (Select Two).

 

A.

Services

B.

Lessons learned

C.

Product
s

D.

Schedule baselines

E.

Resource availability

 

Correct Answer: AC

 

 

QUESTION 230

A project manager has been informed that a project deliverable must be completed by September 1st. Which of the following BEST describes this situation?

 

A.

Project assumption

B.

Project constraint

C.

Project risk

D.

Acceptance criteria

 

Correct Answer: B

 

Free VCE & PDF File for CompTIA JK0-017 Real Exam

Instant Access to Free VCE Files: CompTIA | VMware | SAP …
Instant Access to Free PDF Files: CompTIA | VMware | SAP …