QUESTION 211

A project manager wants to have complete control of the project team members. Which of the following organization structures would allow for this?

 

A.

Functional

B.

Balanced matrix

C.

Strong matrix

D.

Projectized

 

Correct Answer: D

 

QUESTION 212

A stakeholder asks the project manager to finish a project early. The project manager should ask the stakeholder to FIRST:

 

A.

speak to the other stakeholders to get their opinion.

B.

complete a change request form.

C.

speak to the project sponsor.

D.

consider how this might impact the quality of the product.

 

Correct Answer: B

 

 

QUESTION 213

When would a project manager have a closure meeting? (Select Three).

 

A.

Stage completion

B.

Task completion

C.

Document completion

D.

Project cancellation

E.

Project completion

F.

Vendor cancellation

 

Correct Answer: ADE

 

 

QUESTION 214

Which of the following occurs during administrative closure?

 

A.

Requiring input from the sponsor on the project objectives.

B.

Updating quality expectations for the deliverables.

C.

Closing out contracts with vendors.

D.

Revealing new WBS tasks to team members.

 

Correct Answer: C

 

 

QUESTION 215

Before a change request is presented to the change control board, which of the following should the project manager do?

 

A.

Suggest the board study the cost of the change.

B.

Evaluate the affect on all other parts of the project.

C.

Review the change request with the project sponsor.

D.

Request team member input on the value of the change.

 

Correct Answer: B

 

 

QUESTION 216

A project has a CPI of 0.6. Which of the following would BEST describe the cost-efficiency of the project?

 

A.

The costs are currently over the estimates.

B.

The costs and the estimates are about the same.

C.

The costs are currently under the estimates.

D.

The earned value is greater than the actual cost.

 

Correct Answer: A

 

 

QUESTION 217

A stakeholder has indicated that a three phase project must be completed in four months instead of the previously agreed upon six months. It is determined that fast-tracking the project is the only option. Which of the following is a characteristic of fast-tracking a project?

 

A.

Minimizes risk due to decreased timeline.

B.

Requires planning and execution to be completed in parallel.

C.

Minimizes cost since work is completed in four months instead of six.

D.

Requires rework due to decreased timeline.

 

Correct Answer: B

 

 

QUESTION 218

Which of the following are examples of a good business case for a new project? (Select Two).

 

A.

Increased profit opportunity for the customer

B.

Increased billing through maintenance contract

C.

Increased efficiency internally for the customer

D.

Increased engagement length with the customer

E.

Increased billing opportunity for the project team

 

Correct Answer: AC

 

 

QUESTION 219

A project manager seeks to implement a change control system. Which of the following elements are essential for this system to be effective? (Select Three).

 

A.

Change request form

B.

Sponsor communication

C.

Approval mechanism

D.

Pareto chart

E.

Impact analysis

F.

Earned Value (EV) analysis

 

Correct Answer: ACE

 

 

QUESTION 220

Which of the following may require a modification to the project scope baseline?

 

A.

An approved project change request

B.

A team member removed from the project

C.

A task that is falling behind schedule

D.

An identified product quality issue

 

Correct Answer: A

 