[Free] Download New Updated (December) CompTIA JK0-017 Exam Questions 201-210

Ensurepass

QUESTION 201

Cause and effect diagrams are also referred to as:

 

A.

run charts.

B.

Pareto charts.

C.

histograms.

D.

fishbone diagrams.

 

Correct Answer: D

 

 

QUESTION 202

During which of the following process groups is the availability of required resources for the project determined?

 

A.

Executing

B.

Monitoring/Controlling

C.

Initiating

D.

Planning

 

Correct Answer: D

 

 

QUESTION 203

It is important to complete a formal project closure process to: (Select Three).

 

A.

assure that the customer will work with all vendors in the future.

B.

confirm that the stated project objectives were met.

C.

confirm that the customer accepts the final deliverables.

D.

collect new information to enter into the issue log for further review.

E.

assure that the contract is complete and the team members can be released.

F.

collect additional scope requirements that need to be entered into the project plan.

 

Correct Answer: BCE

 

 

QUESTION 204

Which of the following is a tool that can be used to identify project team members that are responsible for a task or deliverable?

 

A.

Project charter

B.

Work Breakdown Structure (WBS)

C.

Project schedule

D.

RACI chart

 

Correct Answer: D

 

 

QUESTION 205

The change control board has approved a change to the scope of a project. Which of the following actions should the project manager take NEXT?

 

A.

Obtain additional approval from the project sponsor.

B.

Discuss this change during the next status meeting.

C.

Perform a probability and impact analysis on the change.

D.

Create a plan to implement the change.

 

Correct Answer: D

 

 

QUESTION 206

A customer is reporting that the projects deliverables are not meeting the acceptance criteria. Which of the following documents MOST likely needs to be updated?

 

A.

Deliverable summary

B.

Quality checklist

C.

Risk register

D.

Resource assignment matrix

 

Correct Answer: B

 

 

QUESTION 207

Which of the following is the primary purpose of a project tollgate?

 

A.

Review the tasks from the next phase of the project.

B.

Review changes to a project.

C.

Get acceptance to move the project to the next phase of work.

D.

Give a status update on a set of deliverables.

 

Correct Answer: C

 

 

QUESTION 208

Which of the following is the main objective for a work breakdown structure (WBS)?

 

A.

To develop a proven methodology t
hat will assist the project manager with the delegation of authority.

B.

To decompose the project down into manageable parts.

C.

To develop the estimating and detailed scheme of the project.

D.

To build on individual development, independent of the team efforts.

 

Correct Answer: B

 

 

QUESTION 209

During the execution of an assigned task the developer informs the project manager of a missing component. Which of the following should the project manager do next?

 

A.

Inform the sponsor and have the developer include it in the same task.

B.

Document the change and determine the impact of the modification.

C.

Add the task to the project plan and assign the task to the developer.

D.

Inform the sponsor that the change is out of scope.

 

Correct Answer: B

 

 

QUESTION 210

Which of the following would be the benefit of saving a project binder in a centralized location?

 

A.

Provides an opportunity for another project manager to review the binder and make corrections.

B.

Provides an opportunity for team members to review their contributions.

C.

Provides other project managers the opportunity to review the project information.

D.

Provides stakeholders the opportunity to modify the change request forms.

 

Correct Answer: C

 

Free VCE & PDF File for CompTIA JK0-017 Real Exam

Instant Access to Free VCE Files: CompTIA | VMware | SAP …
Instant Access to Free PDF Files: CompTIA | VMware | SAP …