QUESTION 181

A project manager has noted that a vendor is providing a poor quality product. The vendor states that its products meet the quality standards outlined in the current contract. Which of the following documents outline the contractual requirements?

 

A.

The statement of work (SOW)

B.

The milestone schedule

C.

The request for proposal (RFP)

D.

The work breakdown structure (WBS)

 

Correct Answer: A

 

 

QUESTION 182

In working with the risk management plan all of the following are ways of dealing with opportunities EXCEPT:

 

A.

exploiting.

B.

mitigating.

C.

sharing.

D.

enhancing.

 

Correct Answer: B

 

 

QUESTION 183

A new project manager has been assigned to a high profile project. In order to determine project status, which of the following should the project manager do? (Select Two).

 

A.

Ask the key stakeholders for the project status.

B.

Leave a voicemail message to key personnel requesting the project status.

C.

Schedule a meeting with the team members to determine the project status.

D.

Send an email to the team members to request project status reports.

E.

Schedule a meeting with the project sponsor to determine the project status.

 

Correct Answer: CD

 

 

QUESTION 184

A company manager has turned in project objectives, and requests that the project manager start the project immediately. The project manager informs the company manager that the project cannot be started. Which of the following is an appropriate reason for not starting the project?

 

A.

Project sponsor approval has not been received.

B.

Projects can only be implemented by upper management.

C.

The project manager already has several ongoing projects.

D.

The project team has not been formed.

 

Correct Answer: A

 

 

 

 

QUESTION 185

A project manager can create a risk breakdown structure (RBS) to determine which of the following?

 

A.

Risk tolerance

B.

Risk probability

C.

Risk category

D.

Risk impact

 

Correct Answer: C

 

 

QUESTION 186

The change control board has just approved a request to modify the sampling technique for a project. Which of the following documents would the project manager update?

 

A.

Risk management plan

B.

Quality management plan

C.

Communication management plan

D.

Scope management plan

 

Correct Answer: B

 

 

QUESTION 187

In pre-project setup, which of the following must be completed prior to validating a project?

 

A.

Project definition

B.

Preliminary SOW

C.

Project charter

D.

Stakeholder approval

 

Correct Answer: A

 

 

QUESTION 188

Which of the following is the BEST reason to conduct a feasibility analysis?

 

A.

To ensure that risks are addressed during the project

B.

To authorize a project

C.

To gather technical data

D.

To assign team member roles

 

Correct Answer: B

 

 

QUESTION 189

Which of the following is a component of the cost management plan?

 

A.

Team member compensation

B.

Statement of Work (SOW)

C.

Project needs assessment

D.

Control limits

Correct Answer: D

 

 

QUESTION 190

The project sponsor indicates that one of the key stakeholders is very unhappy with the project schedule. The other stakeholders are happy with the schedule. Which of the following is the MOST likely reason why the stakeholder is unhappy with the schedule?

 

A.

The stakeholder has unrealistic expectations.

B.

The project manager did not obtain buy-in from the stakeholder.

C.

The project manager did not discuss the schedule with the stakeholders.

D.

The project manager did not schedule the project team appropriately.

 

Correct Answer: B

 