QUESTION 141

A key stakeholder on a project advises the project manager that there is a component of the project that has yet to be decided. They are concerned that their needs regarding this component will not be addressed. In which of the following documents should the project manager record this information?

 

A.

Lessons learned

B.

Issue log

C.

Statement of Work (SOW)

D.

Project charter

 

Correct Answer: B

 

 

QUESTION 142

Which of the following are common causes of project team conflict? (Select Two).

 

A.

Project schedule

B.

Competing resource demands

C.

Project budget

D.

Varying work styles

E.

Time zone differences

 

Correct Answer: BD

 

 

QUESTION 143

Which of the following activities are associated with a project kick-off meeting? (Select Two).

 

A.

Obtaining a signature on the project charter.

B.

Communicating project goals and objectives.

C.

Communicating work package assignments.

D.

Creating a rough draft of the transition plan.

E.

Communicating stakeholder expectations.

 

Correct Answer: BE

 

 

QUESTION 144

Which of the following activities would happen FIRST in procurement management?

 

A.

Request seller responses.

B.

Perform a make or buy analysis.

C.

Perform contract administration.

D.

Perform vendor selection.

 

Correct Answer: B

 

 

QUESTION 145

Which of the following activities occur during a project kick-off meeting? (Select Three).

 

A.

Review of the risk management plan

B.

Review of the roles and responsibilities

C.

Review of the work breakdown structure (WBS)

D.

Review of the change management procedures

E.

Review of the project goals and objectives

F.

Review of the stakeholder expectations

 

Correct Answer: BEF

 

 

QUESTION 146

The amount of time ahead or behind schedule on a project is called the:

 

A.

schedule baseline.

B.

schedule performance index.

C.

estimate to complete.

D.

schedule variance.

 

Correct Answer: D

 

 

QUESTION 147

Which of the following would be the MOST important objective of a kick-off meeting? (Select Two).

 

A.

To educate team members on what will be expected

B.

To give official notification for the project

C.

To inform the project sponsor on what will be expected

D.

To create a work breakdown structure (WBS)

E.

To develop the statement of work (SOW)

 

Correct Answer: AB

 

QUESTION 148

Two employees do not want to work with each other. The project manager tells the employees to perform the tasks or find other employment. Which of the following conflict resolution styles is being used?

 

A.

Forcing

B.

Withdrawing

C.

Compromising

D.

Accepting

 

Correct Answer: A

 

 

QUESTION 149

A project manager sits down to discuss with team members the strengths and weaknesses of a project. This is BEST described as:

 

A.

managing stakeholder expectations.

B.

post-project review.

C.

work performance review.

D.

human resource management.

 

Correct Answer: B

 

 

QUESTION 150

A key stakeholder has asked the project manager to complete the project a week earlier than expected. To
accomplish this objective, the project manager will have to ask the project team to work overtime, which will increase the cost of the project. Which of the following should be the NEXT step?

 

A.

Ask the key stakeholder for more funding for the project.

B.

Ask the project team to work overtime to finish the project.

C.

Obtain an approved change control document before changing the project schedule.

D.

Agree to complete the project using the new schedule.

 

Correct Answer: C

 