QUESTION 11

A project manager is reviewing the ownership, date, and the necessary training for a deliverable. Which of the following documents would include this information?

 

A.

Transition plan

B.

Quality plan

C.

Change Control plan

D.

Procurement plan

 

Correct Answer: A

 

 

QUESTION 12

Which of the following contract types places the LEAS
T amount of risk on the seller?

 

A.

Fixed-Price

B.

Cost-Plus-Fixed-Fee (CPFF)

C.

Cost-Plus-Fee (CPF)

D.

Time and material

 

Correct Answer: D

 

 

QUESTION 13

In which of the following organization types would a project manager have the MOST authority?

 

A.

Projectized

B.

Balanced Matrix

C.

Weak Matrix

D.

Functional

 

Correct Answer: A

 

 

QUESTION 14

Which of the following tools are used for quality planning? (Select Two).

 

A.

Cost / Benefit analysis

B.

Network diagram

C.

Benchmarking

D.

Critical Path Method (CPM)

E.

Parametric estimating

 

Correct Answer: AC

 

 

QUESTION 15

A project manager has failed to obtain the necessary permits from the local building commission. The project has been stopped because of a failure to understand the importance of:

 

A.

internal process compliance.

B.

risk avoidance.

C.

standards compliance.

D.

audit trail compliance.

 

Correct Answer: C

 

 

QUESTION 16

Which of the following would measure a project’s validity?

 

A.

Risk analysis

B.

Strategic alignment

C.

Resource allocation

D.

Gantt chart

 

Correct Answer: B

 

 

QUESTION 17

Which of the following defines a project? (Select Two).

 

A.

Limited time span

B.

Contains more than one deliverable

C.

Delivers a unique product or service

D.

Changes an ongoing process

E.

Generates positive returns

 

Correct Answer: AC

 

 

QUESTION 18

Which of the following describes the point in time when resources can be assigned to scheduled tasks?

 

A.

When the project statement of work (SOW) has been created

B.

When the project deliverables have been defined

C.

When the work breakdown structure (WBS) is decomposed into work packages

D.

When the project WBS dictionary has been created

 

Correct Answer: C

 

 

QUESTION 19

Which of the following are created using information contained in the work breakdown structure (WBS)? (Select Two).

 

A.

Project scope statement

B.

Project statement of work

C.

Project charter

D.

Project activity estimates

E.

Project resource estimates

 

Correct Answer: DE

 

 

QUESTION 20

Several key resources will be unavailable at the end of the project. The key stakeholders want to outsource the project to a third party. Which of the following risk responses is described in this situation?

 

A.

Risk avoidance

B.

Risk mitigation

C.

Risk acceptance

D.

Risk transference

 

Correct Answer: D

 